PKCELL Customized CR123A Battery Packs Ensure Rapid Deployment for North American Safety Systems
Background / Challenge
A North American customer, specializing in home fire and water damage protection systems, faced an extremely tight deadline for exporting a large volume of their devices to the U.S. market. The challenge was heightened by a rapidly closing trade window (August 12, 2025), necessitating swift action to avoid potential tariff increases and market delays. The project's time-sensitive nature placed intense pressure on the battery supplier, requiring:
- Rapid Prototyping: Samples needed to be completed within 3 days for internal testing.
- Accelerated Production: Initial production of 6,000 sets had to be completed within 14 days.
- Logistics Coordination: All 18,000 sets needed to be delivered within 90 days to meet customs and market deadlines.
- Complex Coordination: The project demanded rapid and seamless coordination across R&D, production, and logistics teams.
Solution
PKCELL provided a highly customized CR123A battery solution, specifically a 1S6P and 6S1P 18V 9Ah Battery Pack, designed for the customer's home fire and water damage protection system. Our approach focused on speed, efficiency, and flexible coordination across all internal departments to meet the critical trade window deadline. Key elements of PKCELL's rapid solution included:
- Rapid Sampling: Prototype samples were completed within the strict 3-day timeline, fully meeting all required electrical and performance specifications.
- Accelerated Production: We delivered the first 3,000 sets within the required 14 days for the initial shipment. The remaining 3,000 sets were completed within the next 7 days, ensuring a continuous supply for the customer's device assembly line.
- Flexible Supply Coordination: Production and logistics teams worked in tight synchronization to guarantee on-time delivery despite the challenging schedule and potential trade tension hurdles.
Why PKCELL?
- Agility in Crisis: Our efficient project management and flexible manufacturing capacity enabled our crew to successfully manage a highly time-sensitive project with strict trade deadlines.
- Commitment to Deadlines: We successfully shipped the entire order of 18,000 complete devices within the 90-day trade window.
- Value-Driven Partnership: Our reliable quality and fast delivery helped the customer avoid potential tariff increases and significant market delays, safeguarding their entry into the U.S. market.
- Proven R&D and Production Speed: We proved our capability to move from sample request to initial mass production faster than industry standards (3 days for samples, 14 days for the first batch).